Moving your history across
How long a project management migration actually takes
Six weeks for a single team, eleven to fourteen for a twelve-project portfolio. The step that overruns is almost always the same one, and it is not the data.
The phases, and what each takes
| Phase | Single team | Portfolio |
|---|---|---|
| Decisions: projects, roles, guest access | 0.5 | 2 to 3 |
| Trial import into staging | 1 | 2 |
| Reconciliation and state mapping | 1 | 2 to 3 |
| Automations rebuilt and tested | 1 | 2 |
| Parallel running | 2 | 3 |
| Cutover and source freeze | 0.5 | 1 |
| Total | 6 weeks | 11 to 14 weeks |
The step that overruns
Decisions. Not the import, which is automated and repeatable, but agreeing what counts as a project, which three roles map to which people, and whether clients get guest access.
On a single team that conversation takes an afternoon. Across twelve projects owned by different leads it takes two to three weeks, because the portfolio rollup requires every project to describe status the same way, and that agreement has to be reached before the mapping is written.
A portfolio migration that is running late is usually still in this phase.
Parallel running, and why it is not optional
Both systems stay live for two to three weeks, with Cadenta as the system of record and the source system read-only. Work happens in one place; the other is there to check against.
The purpose is to catch the automations. A rebuilt rule that fires on the wrong transition is invisible in a staging import and obvious within a week of real use.
What you have to supply
- An export or API access to the source system, and someone who can authorize it.
- A decision-maker per project for the state mapping, available in the same two-week window rather than sequentially.
- A list of automations that matter, which is usually shorter than the list that exists.
- A named cutover date, set at the start rather than when parallel running ends.
What shortens it
Fewer workflow states in the source system, a single owner empowered to decide the mapping, and a willingness to archive rather than migrate closed work older than the active window.
The largest single reduction is the decision phase, and it is reduced by having fewer people who can veto the mapping, not by starting earlier.
Frequently asked questions
How long does it take to migrate off a legacy project tracker?
Which phase usually runs late?
Do both systems have to run at once?
More in Moving your history across
- What happens to four years of ticket history when you migrateWhat transfers intact, what is transformed on the way across, and the two things that do not come over at all.
- A portfolio view across twelve projects, without exporting anythingWhat a rollup contains, how it is assembled, and the one report that still needs an export.